Lower throughput due to production disruptions in Aitik

Lower throughput due to production disruptions in Aitik

Due to an unplanned maintenance stop in one of the mill lines and unfavorable weather conditions, throughput in Aitik in the fourth quarter is expected to amount to just over 9 Mton, which is lower than what can be expected based on available information.

An unplanned maintenance stop on one out of two primary mills has occurred as a result of damage between the trunnion and feed end. Production in the affected mill line has been stopped and is expected to restart in December.

In addition, seasonal and unfavorable weather conditions in mid-November have resulted in elevated nitrogen dioxide levels in the air in Aitik. This led to restrictions on large parts of Aitik's industrial area and production was limited.

All in all, this means that Aitik's throughput during the fourth quarter of 2023 is now estimated to amount to just over 9 Mton, compared to just over 11 Mton that can be expected under more normal conditions. Guidance for copper and gold content is not affected by the above production disruptions.

For further information, please contact:

Klas Nilsson, Director Group Communications, phone: +46 70-453 65 88

[email protected] 

This information is information that Boliden AB is obliged to make public pursuant to the EU Market Abuse Regulation. The information was submitted for publication, through the agency of Director Investor Relations, at 08.00 CET on November 29, 2023.

Boliden’s vision is to be the most climate-friendly and respected metal provider in the world. We are Europe’s producer of sustainable metals and, guided by our values care, courage and responsibility, we operate within exploration, mines, smelters and recycling. We are more than 6,000 employees and have annual revenues of approximately SEK 85 billion. The share is listed in the Large Cap segment of NASDAQ OMX Stockholm.

More press releases & news

Den onormalt höga seismiska aktiviteten i Garpenberg har minskat och gruvproduktion på låga nivåer kommer påbörjas under det andra kvartalet. Genomsättningen för det första kvartalet blev knappt 0.8 Mton istället för som förväntat drygt 0.9 Mton till redan kommunicerade halter. Samtliga inspektioner är ännu inte färdigställda men produktion i den mest berörda delen av gruvan bedöms inte kunna återupptas under 2026. Fram till att annat meddelas beräknas Garpenbergs produktion därför uppgå till omkring 30 procent av guidad kapacitet på 3.7 Mton per år. För första kvartalet 2026 påverkas EBITDA negativt med cirka -400 MSEK med dagens priser och villkor.

Aktieägarna i Boliden AB (publ) (

Boliden har beslutat att investera i ett nytt uppfordringsschakt vid Garpenberg och en industriell demonstrationsanläggning för produktion av cementersättning vid Rönnskär. Investeringarna, som uppgår till 4 miljarder SEK respektive 1,5 miljarder SEK, kommer att stärka båda enheternas resultatförmåga och lägga grunden för att utnyttja ytterligare framtida möjligheter.