Lower throughput due to production disruptions in Aitik

Due to an unplanned maintenance stop in one of the mill lines and unfavorable weather conditions, throughput in Aitik in the fourth quarter is expected to amount to just over 9 Mton, which is lower than what can be expected based on available information.

An unplanned maintenance stop on one out of two primary mills has occurred as a result of damage between the trunnion and feed end. Production in the affected mill line has been stopped and is expected to restart in December.

In addition, seasonal and unfavorable weather conditions in mid-November have resulted in elevated nitrogen dioxide levels in the air in Aitik. This led to restrictions on large parts of Aitik's industrial area and production was limited.

All in all, this means that Aitik's throughput during the fourth quarter of 2023 is now estimated to amount to just over 9 Mton, compared to just over 11 Mton that can be expected under more normal conditions. Guidance for copper and gold content is not affected by the above production disruptions.

For further information, please contact:

Klas Nilsson, Director Group Communications, phone: +46 70-453 65 88

[email protected] 

This information is information that Boliden AB is obliged to make public pursuant to the EU Market Abuse Regulation. The information was submitted for publication, through the agency of Director Investor Relations, at 08.00 CET on November 29, 2023.

Boliden’s vision is to be the most climate-friendly and respected metal provider in the world. We are Europe’s producer of sustainable metals and, guided by our values care, courage and responsibility, we operate within exploration, mines, smelters and recycling. We are more than 6,000 employees and have annual revenues of approximately SEK 85 billion. The share is listed in the Large Cap segment of NASDAQ OMX Stockholm.

Downloads

More press releases & news

The abnormally high seismic activity in Garpenberg has decreased and mining production at low levels will commence in the second quarter. The first quarter throughput was just under 0.8 Mton instead of the expected slightly over 0.9 Mton at already communicated grades. All inspections are not yet complete but production in the most affected part of the mine is not expected to resume in 2026. Until further notice, Garpenberg's production is therefore estimated to be around 30 percent of the guided capacity of 3.7 Mton per year. For the first quarter of 2026, EBITDA will be negatively affected by approximately SEK -400 million at today's prices and terms.

The shareholders of Boliden AB (p

Boliden has decided to invest in a new hoist system at Garpenberg and an industrial demonstration plant for the production of supplementary cementitious material at Rönnskär. The investments, which amount to SEK 4 billion and SEK 1.5 billion respectively, will strengthen the earnings capacity of both units and lay the foundation for exploiting further future opportunities.