Production disturbances in Aitik and Tara

Production disturbances in Aitik and Tara

As a result of increased sick leave related to covid-19 together with production disruptions in both the Aitik mine in Sweden and the Tara mine in Ireland, operating profit in the Business Area Mines is estimated to be negatively affected by close to SEK 200 m during the first quarter.

In Aitik, an increased spread of covid-19 and associated sick leave has meant that mine production has not been able to be fully maintained during the first quarter. In addition, hydraulic problems in one out of two primary mills in the concentrator plant have led to production disruptions. The total production impact in Aitik is estimated at just over 1 Mton reduced throughput in addition to seasonal variations.

Also in Tara, increased absenteeism due to Covid-19 has had a negative effect on production. In addition, a breakdown of the ore hoist has occurred in the mine. The breakdown has caused a halt in mining production, which is expected to last for a week.

The total impact on operating profit in the Business Area Mines is estimated at close to SEK  -200 m during the first quarter.

 

For further information, please contact:

Klas Nilsson, Director Group Communications, tel: +46 (0)70-453 65 88

Boliden is a metals company with a focus on sustainable development. Our roots are Nordic, our market global. Our core competence lies within the fields of exploration, mining, smelting and metal recycling. Boliden has around 6,000 employees and an annual turnover of SEK 50 billion. The share is listed in the Large Cap segment on NASDAQ OMX Stockholm.

More press releases & news

Den onormalt höga seismiska aktiviteten i Garpenberg har minskat och gruvproduktion på låga nivåer kommer påbörjas under det andra kvartalet. Genomsättningen för det första kvartalet blev knappt 0.8 Mton istället för som förväntat drygt 0.9 Mton till redan kommunicerade halter. Samtliga inspektioner är ännu inte färdigställda men produktion i den mest berörda delen av gruvan bedöms inte kunna återupptas under 2026. Fram till att annat meddelas beräknas Garpenbergs produktion därför uppgå till omkring 30 procent av guidad kapacitet på 3.7 Mton per år. För första kvartalet 2026 påverkas EBITDA negativt med cirka -400 MSEK med dagens priser och villkor.

Aktieägarna i Boliden AB (publ) (

Boliden har beslutat att investera i ett nytt uppfordringsschakt vid Garpenberg och en industriell demonstrationsanläggning för produktion av cementersättning vid Rönnskär. Investeringarna, som uppgår till 4 miljarder SEK respektive 1,5 miljarder SEK, kommer att stärka båda enheternas resultatförmåga och lägga grunden för att utnyttja ytterligare framtida möjligheter.