Boliden postpones Åkulla expansion

Boliden postpones Åkulla expansion

As a consequence of the Environmental Court's rejection of Boliden's application for building a new tailings pond in the Boliden area Boliden has decided to postpone the expansion at its Åkulla mineralisation in the area. As a consequence of the ruling Boliden will be forced to give 51 employees in the mining area notice of redundancy.

The Environmental Court's negative ruling on 24th March concerning a new, expanded tailings pond is not compatible with future production at current levels in the Boliden area. As of the first quarter of 2007, production in the mining area is therefore expected to decline by about 10 per cent compared with current production levels. Altogether, the forecast cutback is expected to lead to a decrease in Boliden's planned mining production of copper and zinc by around 1 and 2 per cent respectively. It will be possible to compensate, at least in part, for this decline in production in the event of a positive ruling by the Environmental Court of Appeal.

 "We had planned to have the new tailings pond - the Hötjärn tailings pond - operational in 2008. The negative ruling by the Environmental Court means that a future tailings pond cannot become operational until 2009 at the earliest. We are now lodging an appeal against the ruling, although the legal proceedings are expected to take so long that measures have to be implemented immediately," says Jan Moström, President - Business Area Mines.
 
In consultation with trade union organisations, among others, Boliden plans to seek solutions that will minimise redundancies.
 Boliden is one of the world's leading mining and smelting companies with operating facilities in Sweden, Finland, Norway and Ireland. Boliden mainly produces copper, zinc and lead, as well as gold and silver. Other important operations include mineral exploration and metal recycling. The company has around 4,500 employees and net sales of almost SEK 20 billion. Its shares are listed on Stockholmsbörsen's O-list and on the Toronto Stock Exchange in Canada.
 						www.boliden.com

For more information, please contact:
Jan Johansson, President and CEO, Boliden AB, tel: +46 (0)8-610 1602, +46 (0)70-555 02 02
Ulf Söderström, Senior Vice President of Communication, Boliden AB, tel: +46 (0)8-610 15 57, +46 (0)70-618 95 95
Jan Moström, President - Business Area Mines, tel: +46 (0)910- 77 42 10, +46 (0)70-673 52 99

More press releases & news

Den onormalt höga seismiska aktiviteten i Garpenberg har minskat och gruvproduktion på låga nivåer kommer påbörjas under det andra kvartalet. Genomsättningen för det första kvartalet blev knappt 0.8 Mton istället för som förväntat drygt 0.9 Mton till redan kommunicerade halter. Samtliga inspektioner är ännu inte färdigställda men produktion i den mest berörda delen av gruvan bedöms inte kunna återupptas under 2026. Fram till att annat meddelas beräknas Garpenbergs produktion därför uppgå till omkring 30 procent av guidad kapacitet på 3.7 Mton per år. För första kvartalet 2026 påverkas EBITDA negativt med cirka -400 MSEK med dagens priser och villkor.

Aktieägarna i Boliden AB (publ) (

Boliden har beslutat att investera i ett nytt uppfordringsschakt vid Garpenberg och en industriell demonstrationsanläggning för produktion av cementersättning vid Rönnskär. Investeringarna, som uppgår till 4 miljarder SEK respektive 1,5 miljarder SEK, kommer att stärka båda enheternas resultatförmåga och lägga grunden för att utnyttja ytterligare framtida möjligheter.