Boliden granted environmental permit for production expansion to 36 million tonnes at the Aitik mine

Boliden granted environmental permit for production expansion to 36 million tonnes at the Aitik mine

The Environmental Court announced today that Boliden has been granted a permit for the expansion of the Aitik mine from the current annual production of 18 million tonnes to 36 million tonnes.

Already in October 2007, the Environmental Court ruled that the planned expansion is permissible and granted Boliden permit to commence certain construction work. Today's ruling means that Boliden can now continue the expansion of the Aitik mine as planned.

The permit stipulates conditions for air and water emissions, noise and other environmental impact, among other things. It also includes requirements regarding remediation as well as economic guarantees for remediation costs totalling SEK 660 million. The Environmental Court has essentially accepted Boliden's proposed conditions.

The expansion of the Aitik mine entails an investment of approximately SEK 5.2 billion. Ore production capacity will increase to 33 million tonnes in 2010 and reach full capacity in 2014.

Boliden is one of the leading mining and smelting companies in Europe with operations in Sweden, Finland, Norway and Ireland. Boliden's main products are copper, zinc, lead and gold and silver. Exploration and recycling of metals are also important within the company. The number of employees is approximately 4 500 and the turnover amounts to approximately EUR 3.8 billion annually. Its shares are listed on Stockholmsbörsen's Large Cap list and on the Toronto Stock Exchange in Canada.

www.boliden.com

For further information, please contact:
Jan Moström, President, Business Area Mines, tel. +46 910-77 42 10, +46 70-673 52 99
Eva Kaijser, Senior Vice President, Investor Relations and Group Communications Boliden AB, tel. +46 8-610 1560, +46 709-320 901

More press releases & news

Den onormalt höga seismiska aktiviteten i Garpenberg har minskat och gruvproduktion på låga nivåer kommer påbörjas under det andra kvartalet. Genomsättningen för det första kvartalet blev knappt 0.8 Mton istället för som förväntat drygt 0.9 Mton till redan kommunicerade halter. Samtliga inspektioner är ännu inte färdigställda men produktion i den mest berörda delen av gruvan bedöms inte kunna återupptas under 2026. Fram till att annat meddelas beräknas Garpenbergs produktion därför uppgå till omkring 30 procent av guidad kapacitet på 3.7 Mton per år. För första kvartalet 2026 påverkas EBITDA negativt med cirka -400 MSEK med dagens priser och villkor.

Aktieägarna i Boliden AB (publ) (

Boliden har beslutat att investera i ett nytt uppfordringsschakt vid Garpenberg och en industriell demonstrationsanläggning för produktion av cementersättning vid Rönnskär. Investeringarna, som uppgår till 4 miljarder SEK respektive 1,5 miljarder SEK, kommer att stärka båda enheternas resultatförmåga och lägga grunden för att utnyttja ytterligare framtida möjligheter.