Boliden's mining and smelting production was stable and in line with planned production levels during the third quarter of 2005.

Product Segment Copper
Third quarter copper concentrate production levels at the Aitik mine in 2005 were considerably up on levels for the second quarter of the year, but down on figures for the third quarter of 2004. The head grades of the ores mined have successively improved throughout 2005.

The smelters at Rönnskär and Harjavalta reported good production levels for copper cathodes during the third quarter after the planned maintenance shutdowns in the second quarter. Rönnskär also processed a higher percentage of electronic scrap during the third quarter. The primary effect of this was to boost gold production whereas lead production levels fell. Harjavalta also successfully recommenced nickel smelting two weeks earlier than anticipated after the temporary stoppage caused by a shortage of nickel concentrate.

Product Segment Zinc
The combined production of zinc concentrate from the mines in the Boliden Area, Garpenberg and Tara was higher in the third quarter of 2005 than in both the second quarter of this year and the third quarter of 2004. Repairs after the breakdown in the grinding mills at Tara in the second quarter of 2005 were completed according to plan and Tara returned to full production as of mid-July.

The combined production of the Boliden Kokkola and Boliden Odda zinc smelters was consistent and stable during the third quarter of 2005, and levels were on a par with those for the second quarter of this year and the corresponding quarter in 2004.

Boliden's Interim Report for January-September 2005 will be published October 25, 2005.

Appendix 1. Metal production, exchange rates and metal prices for Q3 2005.

Boliden is one of the world's leading mining and smelting companies with operating facilities in Sweden, Finland, Norway and Ireland. Boliden mainly produces copper, zinc and lead, as well as gold and silver. Other important operations include mineral exploration and metal recycling. The company has around 4,500 employees and net sales of almost SEK 18 billion. Its shares are listed on Stockholmsbörsen's O-list and on the Toronto Stock Exchange in Canada.
www.boliden.com

For more information, please contact:

Jan Johansson, President and CEO, Boliden AB, tel +46 8 610 16 02, +46 70 555 02 02
Staffan Bennerdt, CFO, Boliden AB, tel +46 8 610 15 20, +46 70 513 61 14
Ulf Söderström, Senior Vice President, Group Communications, Boliden AB,
tel +46 8 610 15 57, +46 70 618 95 95

More press releases & news

The abnormally high seismic activity in Garpenberg has decreased and mining production at low levels will commence in the second quarter. The first quarter throughput was just under 0.8 Mton instead of the expected slightly over 0.9 Mton at already communicated grades. All inspections are not yet complete but production in the most affected part of the mine is not expected to resume in 2026. Until further notice, Garpenberg's production is therefore estimated to be around 30 percent of the guided capacity of 3.7 Mton per year. For the first quarter of 2026, EBITDA will be negatively affected by approximately SEK -400 million at today's prices and terms.

The shareholders of Boliden AB (p

Boliden has decided to invest in a new hoist system at Garpenberg and an industrial demonstration plant for the production of supplementary cementitious material at Rönnskär. The investments, which amount to SEK 4 billion and SEK 1.5 billion respectively, will strengthen the earnings capacity of both units and lay the foundation for exploiting further future opportunities.