Higher provisions for future reclamation of Aitik and Garpenberg

Due to more extensive reclamation plans for Aitik and Garpenberg, Boliden's provisions for reclamation are increased by SEK 3.8 billion. As a result, annual depreciation increases by approximately SEK 200 million and the financial net is negatively affected by approximately SEK 100 million starting in 2024. The result for the fourth quarter of 2023 is not affected. The cash flow impact due to reclamation work mainly only occurs when mines are closed.

Most of the extended provisions for reclamation are related to Aitik soon will submit a new application for an operating permit. In connection with this, the proposed provision for reclamation will be based on the entire life of mine, which today extends until 2047.

 

“With new permits and improved dam construction, we have created long-term conditions for Aitik to continue to be the world's most productive copper mine. It also gives us room to both plan and implement reclamation efforts in the best possible way,” says Stefan Romedahl, director Business Area Mines.

 

In Garpenberg, certain technical adjustments to the reclamation plan for the tailings facility have been made, which affects the now expanded provisions for reclamation. Garpenberg´s life of mine, according to current Mineral Resources and Mineral Reserves, stretches to 2055 given present pace of production.

 

All in all, this means that Boliden's provisions for reclamation will be increased by SEK 3.8 billion from today's SEK 7.4 billion. The Group's net reclamation liability is not affected due to a corresponding increase in assets. From 2024, the increased assets will lead to increased annual depreciation by approximately SEK 200 million and the increased reclamation liability will also affect the financial net negatively by approximately SEK 100 million per year, as a result of discounting effects. The income statement for the fourth quarter of 2023 is not affected.

 

The cash flow impact due to reclamation work mainly only occurs when mines are closed.

 

 

For further information, please contact:

Klas Nilsson, Director Group Communications, phone: +46 70-453 65 88, [email protected]

 

 

This information is information that Boliden AB is obliged to make public pursuant to the EU Market Abuse Regulation. The information was submitted for publication, through the agency of Director Investor Relations, at 08.00 CET on November 16, 2023. 

 

 

Boliden is a metals company with a focus on sustainable development. Our roots are Nordic, our market global. Our core competence lies within the fields of exploration, mining, smelting and metal recycling. Boliden has around 6,000 employees and annual sales of approximately SEK 85 billion. The share is listed in the Large Cap segment on NASDAQ OMX Stockholm. www.boliden.com

Downloads

More press releases & news

The abnormally high seismic activity in Garpenberg has decreased and mining production at low levels will commence in the second quarter. The first quarter throughput was just under 0.8 Mton instead of the expected slightly over 0.9 Mton at already communicated grades. All inspections are not yet complete but production in the most affected part of the mine is not expected to resume in 2026. Until further notice, Garpenberg's production is therefore estimated to be around 30 percent of the guided capacity of 3.7 Mton per year. For the first quarter of 2026, EBITDA will be negatively affected by approximately SEK -400 million at today's prices and terms.

The shareholders of Boliden AB (p

Boliden has decided to invest in a new hoist system at Garpenberg and an industrial demonstration plant for the production of supplementary cementitious material at Rönnskär. The investments, which amount to SEK 4 billion and SEK 1.5 billion respectively, will strengthen the earnings capacity of both units and lay the foundation for exploiting further future opportunities.