Environmental permit for expanded production in Garpenberg granted

Boliden has been granted an environmental permit for an increase in the annual production rate in Garpenberg. As a result of the decision, bottleneck investments can be initiated with the aim of increasing production to 3.3 Mtons per year.  

“This is a very welcome decision that gives us the opportunity to continue to strengthen productivity in Garpenberg. In addition, we are meeting increased demand with additional zinc with world-leading sustainability performance, says Stefan Romedahl, President Business Area Mines, Boliden.

Production in Garpenberg today amounts to approximately 3 Mtons at an annual rate, which has also been the highest permitted volume within the existing environmental permit. The new environmental permit means, among other things, that capacity reinforcements in the transport infrastructure can be initiated with a focus on reaching a production volume of 3.3 Mtons in 2023. The environmental permit follows a decision from Land and Environmental Court of Appeal not to grant appeal. The decision can be appealed to the Supreme Court until 1 November 2021.

-------------------------

For further information, please contact:

Klas Nilsson, Director Group Communications, tel: +46 (0)70-453 65 88

 

 

Boliden is a metals company with a focus on sustainable development. Our roots are Nordic, our market global. Our core competence lies within the fields of exploration, mining, smelting and metal recycling. Boliden has around 6,000 employees and an annual turnover of SEK 50 billion. The share is listed in the Large Cap segment on NASDAQ OMX Stockholm. 

More press releases & news

The abnormally high seismic activity in Garpenberg has decreased and mining production at low levels will commence in the second quarter. The first quarter throughput was just under 0.8 Mton instead of the expected slightly over 0.9 Mton at already communicated grades. All inspections are not yet complete but production in the most affected part of the mine is not expected to resume in 2026. Until further notice, Garpenberg's production is therefore estimated to be around 30 percent of the guided capacity of 3.7 Mton per year. For the first quarter of 2026, EBITDA will be negatively affected by approximately SEK -400 million at today's prices and terms.

The shareholders of Boliden AB (p

Boliden has decided to invest in a new hoist system at Garpenberg and an industrial demonstration plant for the production of supplementary cementitious material at Rönnskär. The investments, which amount to SEK 4 billion and SEK 1.5 billion respectively, will strengthen the earnings capacity of both units and lay the foundation for exploiting further future opportunities.