Decision in the dispute between Junta de Andalucia and Boliden

The district court in Seville has today announced its decision in the financial dispute between the Junta de Andalucia and Boliden. The court has found that Boliden is not liable for the claim of roughly EUR 89 million that the Junta de Andalucia directed against the company regarding clean-up costs in connection with a dam failure in 1998 at Boliden's former operation Apirsa in Spain.

"While the dam accident was extremely unfortunate, the decision of the court confirms our view that the extensive clean-up efforts that Boliden carried out and the compensation at the time of the accident were satisfactory and that Boliden thereby has acted promptly and in a responsible manner," says Mikael Staffas, President and CEO.

The decision can be appealed to the next instance.

In 1998, an accident took place in the Apirsa mine in Andalusia when a dam failure occurred at the mine. Although the environmental impact was extensive, no people were injured in connection with the accident. Very extensive and successful clean-up efforts were carried out by both Boliden and the authorities. Already one year later, the mine could be reopened, but a few years later the mine was closed as a result of low world market prices. The accident was likely caused by construction errors on the dam body, which was constructed several years before the mine came into Boliden's ownership.

Boliden's vision is to be the most climate-friendly and respected metal provider in the world. We are Europe's producer of sustainable metals and, guided by our values care, courage and responsibility, we operate within exploration, mines, smelters and recycling. We are more than 6,000 employees and have annual revenues of approximately SEK 85 billion. The share is listed in the Large Cap segment of NASDAQ OMX Stockholm. www.boliden.com

For further information, please contact: 

Klas Nilsson
Director of Group Communications
tel: +46 (0)70 453 65 88
Mail: [email protected]

Downloads

More press releases & news

The abnormally high seismic activity in Garpenberg has decreased and mining production at low levels will commence in the second quarter. The first quarter throughput was just under 0.8 Mton instead of the expected slightly over 0.9 Mton at already communicated grades. All inspections are not yet complete but production in the most affected part of the mine is not expected to resume in 2026. Until further notice, Garpenberg's production is therefore estimated to be around 30 percent of the guided capacity of 3.7 Mton per year. For the first quarter of 2026, EBITDA will be negatively affected by approximately SEK -400 million at today's prices and terms.

The shareholders of Boliden AB (p

Boliden has decided to invest in a new hoist system at Garpenberg and an industrial demonstration plant for the production of supplementary cementitious material at Rönnskär. The investments, which amount to SEK 4 billion and SEK 1.5 billion respectively, will strengthen the earnings capacity of both units and lay the foundation for exploiting further future opportunities.