Boliden's Tara zinc mine in Ireland back in full production

 Boliden's zinc mine Tara in Ireland is now back in full production since the mill breakdown has been repaired. The effect on the operating results will be, as earlier reported, over SEK 40 million. The company will now be able to completely fulfil its contracted deliveries for the remainder of the year and therefore lifts its earlier declared partial Force Majeure.    

The direct effect of the motor breakdown at one of the grinding mills involved in the milling process was a decline of the production of the zinc and lead concentrate by around 40 per cent. However, the metal production at Boliden's own zinc smelters, Boliden Kokkola and Boliden Odda, were not, as earlier predicted, affected having compensated the short fall from own inventories at the smelters.

Boliden's Tara zinc mine has a production capacity of approximately 400,000 tonnes of zinc concentrate and approximately 50,000 tonnes of lead concentrate per year.

For more information, please contact:

Jan Johansson, President and CEO, Boliden AB, tel.: +46 (0)8 610 1602, +46 (0)70 555 02 02
Ulf Söderström, Senior Vice President, Group Communications, Boliden AB,
tel.: +46 (0)8 610 15 57, +46 (0)70 618 95 95

 Boliden is one of the world's leading mining and smelting companies with operating facilities in Sweden, Finland, Norway and Ireland. Boliden mainly produces copper, zinc and lead, as well as gold and silver. Other important operations include mineral exploration and metal recycling. The company has around 4,500 employees and net sales of almost SEK 18 billion. Its shares are listed on Stockholmsbörsen's O-list and on the Toronto Stock Exchange in Canada.
 						  							            www.boliden.com

More press releases & news

The abnormally high seismic activity in Garpenberg has decreased and mining production at low levels will commence in the second quarter. The first quarter throughput was just under 0.8 Mton instead of the expected slightly over 0.9 Mton at already communicated grades. All inspections are not yet complete but production in the most affected part of the mine is not expected to resume in 2026. Until further notice, Garpenberg's production is therefore estimated to be around 30 percent of the guided capacity of 3.7 Mton per year. For the first quarter of 2026, EBITDA will be negatively affected by approximately SEK -400 million at today's prices and terms.

The shareholders of Boliden AB (p

Boliden has decided to invest in a new hoist system at Garpenberg and an industrial demonstration plant for the production of supplementary cementitious material at Rönnskär. The investments, which amount to SEK 4 billion and SEK 1.5 billion respectively, will strengthen the earnings capacity of both units and lay the foundation for exploiting further future opportunities.