Boliden prepares for the inauguration of the Garpenberg expansion

The inauguration ceremony for Boliden’s expansion of the Garpenberg mine will be held on 26 August 2014 with Christer Fuglesang, Professor at the Royal Institute of Technology and the first Swede in space, officiating. The investment, which totalled SEK 3.9 billion, has made Garpenberg into one of the world’s most cost-effective and modern zinc and silver mines.  

The expansion, which is located adjacent to the existing mining area, includes a new concentrator and underground equipment and infrastructure. On the opening day the 150 invited guests will be offered a tour of the new facilities, both above and below ground.

The theme of the inauguration is know-how and technological development, in that the expansion was enabled by a combination of successful exploration activities and sector-leading technological development.

“There are a lot of people and a lot of combined know-how involved in an expansion project on this sort of scale. In addition to our own expertise in a variety of areas, the project has seen us working hand in hand with everyone from our contractors to official bodies and banks. The inauguration day is intended to showcase the importance of new technology in the form of a mine that has been in operation for 800 years now. We are working hard on the preparations for the opening day and are looking forward to showing off the new Garpenberg to all of our guests,” says Marcela Sylvander, Boliden’s Director Group Communications.

Facts and figures:
Mining of the deposits at Garpenberg, outside Hedemora, began way back in the 13th century and the oldest letters patent still in existence for mining operations at Garpenberg were issued in 1354 by the Swedish King Magnus Eriksson, making Garpenberg one of the oldest mines that is still operational. Boliden acquired Garpenberg in 1957, since when exploration work has resulted in a substantial increase in the ore reserves. Today Garpenberg produces complex ores containing zinc, copper, lead, gold and silver – a metal mix that has helped bring about the mine’s favourable cost position.

In 2013, Garpenberg produced:
Ore: 1,495 ktonnes, Zinc: 70,267 tonnes, Copper: 517 tonnes, Lead: 25,352 tonnes, Gold: 277 kg and Silver: 161,784 kg.

  
For further information, please contact:
Marcela Sylvander, Group Communication, +46 733 244551

More press releases & news

The abnormally high seismic activity in Garpenberg has decreased and mining production at low levels will commence in the second quarter. The first quarter throughput was just under 0.8 Mton instead of the expected slightly over 0.9 Mton at already communicated grades. All inspections are not yet complete but production in the most affected part of the mine is not expected to resume in 2026. Until further notice, Garpenberg's production is therefore estimated to be around 30 percent of the guided capacity of 3.7 Mton per year. For the first quarter of 2026, EBITDA will be negatively affected by approximately SEK -400 million at today's prices and terms.

The shareholders of Boliden AB (p

Boliden has decided to invest in a new hoist system at Garpenberg and an industrial demonstration plant for the production of supplementary cementitious material at Rönnskär. The investments, which amount to SEK 4 billion and SEK 1.5 billion respectively, will strengthen the earnings capacity of both units and lay the foundation for exploiting further future opportunities.