Boliden invests in new cleaning system at Rönnskär

Boliden is investing SEK 101 million in a new cleaning system for process gases emitted from the copper smelter at Rönnskär, Skelleftehamn. The investment will lead to a capacity increase corresponding to 15,000 tonnes of finished copper per year as well as an increase in the annual results of approximately SEK 40 million.

"This investment will generate both increased revenues and cut costs," says Jan Johansson, President and CEO for Boliden. The new cleaning system means that the throughput at Rönnskär's smelting facilities can be further increased and that the converter hall, where raw copper is produced, will become more efficient.

The investment comprises a new dust filter, based on hot gas EGR-technology, as well as peripheral equipment and installations. In addition to a reduction in dust emissions, the new gas cleaning system will also reduce maintenance and deposit costs. The system is expected to come on-line in autumn 2007.

For further information, please contact:
Jan Johansson, President and CEO, Boliden AB, tel: +46 (0)8-610 1602, +46 (0)70-555 02 02
Ulf Söderström, Senior Vice President of Communication, Boliden AB, tel: +46 (0)8-610 15 57, +46 (0)70-618 95 95
Roger Sundqvist, General Manager, Rönnskär, tel: +46 (0)910-77 34 00, +46 (0)70-399 72 91

Boliden is one of the leading mining and smelting companies in Europe with operations in Sweden, Finland, Norway and Ireland. Boliden's main products are copper, zinc, lead and gold and silver. Exploration and recycling of metals are also important within the company. The number of employees is approximately 4 500 and the turnover amounts to approximately EUR 2.2 billion annually. Its shares are listed on Stockholmsbörsen's O-list and on the Toronto Stock Exchange in Canada.

www.boliden.com

More press releases & news

The Nomination Committee of Boliden AB (publ) proposes that Victoire de Margerie is elected as new Board Member at the Annual General Meeting ("AGM") on April 23, 2025. Further, the Nomination Committee proposes re-election of all current Board Members

In connection with a new pushback in Aitik, production challenges have arisen as a result of high deposits of the very hard rock type diorite. The occurrences create challenges and mean that the production rate for the first quarter is estimated to be just over 9 Mtonnes. For the full year 2025, production is estimated at close to 40 Mtonnes. The copper grade is estimated at 0.16%, which is in line with what was previously communicated.

Boliden AB (LEI code: 21380059QU7IM1ONDJ56) has during February 7 and 10, 202