Boliden invests in improved logistics for Harjavalta smelter

Boliden has decided to invest 40 MEUR in long-term improvements of infrastructure at the Port of Pori, thus improving conditions for handling of concentrates to Harjavalta. The investment will be carried out during 2021-2022 and the facilities will be operational in the beginning of 2023.

To improve the standard of operations at Port of Pori, Boliden has decided to invest in improved environmental performance as well as commercial handling. The investment includes building a weighing and sampling facility and a new warehouse. In addition, the Port of Pori carries out investment to a new quay and its infrastructure.

“Through the infrastructure modernization of the Port of Pori, we are taking further steps in strengthening our productivity and competitiveness as well as contributing to our strong environmental performance,” says Daniel Peltonen, President of Business Area Smelters.

The investment is within the framework of Boliden’s total investment plan at just over SEK 7 billion in 2021.

 

For further information, please contact:
Klas Nilsson, Director Group Communications, tel: +46 (0)70-453 65 88
Timo Rautalahti, General manager, Boliden Harjavalta Oy, tel: +358(0)50-598 7620


Boliden is a metals company with a focus on sustainable development. Our roots are Nordic, our market global. Our core competence lies within the fields of exploration, mining, smelting and metal recycling. Boliden has around 6,000 employees and an annual turnover of SEK 50 billion. The share is listed in the Large Cap segment on NASDAQ OMX Stockholm. 

 

More press releases & news

The abnormally high seismic activity in Garpenberg has decreased and mining production at low levels will commence in the second quarter. The first quarter throughput was just under 0.8 Mton instead of the expected slightly over 0.9 Mton at already communicated grades. All inspections are not yet complete but production in the most affected part of the mine is not expected to resume in 2026. Until further notice, Garpenberg's production is therefore estimated to be around 30 percent of the guided capacity of 3.7 Mton per year. For the first quarter of 2026, EBITDA will be negatively affected by approximately SEK -400 million at today's prices and terms.

The shareholders of Boliden AB (p

Boliden has decided to invest in a new hoist system at Garpenberg and an industrial demonstration plant for the production of supplementary cementitious material at Rönnskär. The investments, which amount to SEK 4 billion and SEK 1.5 billion respectively, will strengthen the earnings capacity of both units and lay the foundation for exploiting further future opportunities.