Boliden continues to grow organically

Boliden's Board of Directors has resolved to invest SEK 250 million in a new autogenous grinding mill at the company's Tara Mine in Ireland. At the same time, the Group management has resolved to go ahead with the investigation into increasing capacity for recycling of electronic scrap and lead refining at the Rönnskär copper smelter.

The projects are entirely in line with Boliden's strategies - to invest in internal growth projects and to develop and expand the electronic scrap recycling operations. Organic growth projects within the Group are currently underway to the amount of approximately SEK 6.1 billion, the largest of which is the SEK 5.2 billion Aitik project.

The investment at Boliden's zinc mine, Tara, will cut operating costs for grinding by 50 per cent. Together with previous investments at Tara, e.g. in dewatering, the overall operating costs for the concentrator will be reduced by 30 per cent. By replacing the existing crushing and grinding system with a new circuit for autogenous grinding, Boliden expects to increase the zinc yield and improve the work environment through noise and dust reduction. The project is scheduled to be concluded by the end of 2009.

 "Our pre-feasibility study into a capacity increase for electronic scrap recycling and lead refining at the Rönnskär copper smelter has progressed to the next phase. The preconditions for doubling capacity will be further investigated in a feasibility study, due to be completed at the turn of the year. This is mainly a question of establishing technologies and the investment level," says Svante Nilsson, President, Business Area Smelters at Boliden.
 Boliden is one of the leading mining and smelting companies in Europe with operations in Sweden, Finland, Norway and Ireland. Boliden's main products are copper, zinc, lead and gold and silver. Exploration and recycling of metals are also important within the company. The number of employees is approximately 4 500 and the turnover amounts to approximately EUR 3.8 billion annually. Its shares are listed on Stockholmsbörsen's Large Cap list and on the Toronto Stock Exchange in Canada.
 						             
 www.boliden.com

For further information please contact:

Svante Nilsson, President, Business Area Smelters, tel +46 8-610 1527, +46 70-583 3278
Jan Moström, President, Business Area Mines, tel +46 910-774210, +46 70-673 5299
Eva Kaijser, Senior Vice President Information and Investor Relations, Boliden AB, tel: +46 8-610 1560, +46 709-320 901

More press releases & news

The abnormally high seismic activity in Garpenberg has decreased and mining production at low levels will commence in the second quarter. The first quarter throughput was just under 0.8 Mton instead of the expected slightly over 0.9 Mton at already communicated grades. All inspections are not yet complete but production in the most affected part of the mine is not expected to resume in 2026. Until further notice, Garpenberg's production is therefore estimated to be around 30 percent of the guided capacity of 3.7 Mton per year. For the first quarter of 2026, EBITDA will be negatively affected by approximately SEK -400 million at today's prices and terms.

The shareholders of Boliden AB (p

Boliden has decided to invest in a new hoist system at Garpenberg and an industrial demonstration plant for the production of supplementary cementitious material at Rönnskär. The investments, which amount to SEK 4 billion and SEK 1.5 billion respectively, will strengthen the earnings capacity of both units and lay the foundation for exploiting further future opportunities.